justice authorizes the Aubervilliers training pool project

The Paris Administrative Court of Appeal validated, Thursday, July 7, the training pool project in Aubervilliers (Seine-Saint-Denis) for the Paris 2024 Olympic Games (OG), the new version of which preserves the adjoining allotments. “The project on which the court ruled had evolved very clearly compared to the initial project”considered that court in a communicated.

“Two modifying permits have been issued, which have profoundly modified the original project by first removing the restaurant initially planned, then the equipment which was to encroach on the perimeter of the allotment gardens, in particular the mineral beach, the fitness area and well-being and the solarium that were in the first project »she justified.

Judicial arm wrestling

Located near Paris, the aquatic center must be finalized in time to allow Olympic athletes to train there before the events, before welcoming the general public after the Olympics. But its initial location, straddling century-old allotments, had aroused the ire of environmental defenders who engaged in a legal standoff.

Read also: Article reserved for our subscribers “Let’s preserve the allotment gardens of Aubervilliers threatened by an Olympic swimming pool”

To obtain this validation, the city of Aubervilliers, obliged to review its copy, presented the judge with a new version of the project. It has, for this, excluded the object of all tensions: the construction of a “sunroom”a sort of mineral terrace nibbling at 4,000 m2 of food plots on the 2.5 hectares (25,000 m2) of the gardens of Virtues. Opponents saw in this additional equipment a symbol of the “concreting” which further asphyxiates cities, contrary, according to them, to the ecological emergency.

Damage to biodiversity

These works would have caused “consequences that are difficult to reverse” in this “primary nucleus of biodiversity”, had estimated the judge in chambers in March, summoning the city to immediately stop this part of the site. The gardens concerned had already been destroyed by the backhoe loaders.

Read also: Article reserved for our subscribers Olympic Games 2024: the construction of the Aubervilliers swimming pool undermines biodiversity

“There will be no construction, the project has been abandoned. The solarium will not be done”, said Thursday, the city of Aubervilliers to Agence France-Presse. On the other part of the site, “two cranes were installed in June to prepare for the resumption of work”, she added. The earthwork is “in progress” and the big work must start “by the end of July”.

Delivery of the equipment is scheduled for “April 2024”just in time for the Olympic Games which will take place from July 26th to August 11th.

Read also Article reserved for our subscribers The 1,000 office and housing projects that densify Greater Paris

The World with AFP

source site-30