Spie installs two sections of very high voltage line for Amprion in Germany


May 31 (Reuters) – Spie SA:

* GERMANY: SPIE INSTALLS TWO SECTIONS OF VERY HIGH VOLTAGE LINE ON BEHALF OF AMPRION

* INSTALLS TWO SECTIONS OF VERY HIGH VOLTAGE OVERHEAD POWER LINE (ABOUT 25 KM IN TOTAL) BETWEEN METTERNICH AND NIEDERSTEDEM FOR AMPRION

* THE EXISTING LINE CURRENTLY IN SERVICE WILL ALSO BE UPGRADED FROM 220 KV TO 380 KV VOLTAGE LEVEL

* WORK STARTED IN THE FIRST QUARTER OF 2023 AND IS EXPECTED TO COMPLETE IN THE THIRD QUARTER OF 2025












©2023 Thomson Reuters, all rights reserved. Reuters content is the intellectual property of Thomson Reuters or its third party content providers. Any copying, republication or redistribution of Reuters content, including by framing or similar means, is expressly prohibited without the prior written consent of Thomson Reuters. Thomson Reuters shall not be liable for any errors or delays in content, or for any actions taken in reliance thereon. “Reuters” and the Reuters Logo are trademarks of Thomson Reuters and its affiliated companies.



Source link -87