Siemens Energy hands over to Gazprom the documentation for the transport of the Nord Stream 1 turbine -media


Nord Stream 1, which runs on the bed of the Baltic Sea from Russia to Germany, started pumping gas again on Thursday after a 10-day maintenance shutdown, but only at 40% capacity.

Gazprom said on Friday that it had still not obtained the necessary documents from Siemens Energy confirming the exemption from European Union and Canadian sanctions for the return of a key turbine for the pipeline at the Portovaya compressor station. from Nord Stream. The turbine had been sent to Canada for repair.

Kommersant, without citing sources, said that due to a lack of necessary paperwork, the turbine, which was on its way back from Canada to Russia, missed a ferry from Germany to Helsinki on Saturday.

He said the turbine could be delivered in the next few days if Siemens Energy and Gazprom change the necessary documents.

Kommersant also said the delivery of the turbine may not result in increased gas deliveries through Nord Stream 1 as several units need to be repaired at the Portovaya compressor station.

Siemens Energy declined to comment, Gazprom did not respond to repeated requests for comment.

Gazprom cut off Nord Stream 1 flows in June, saying it could not retrieve the turbine from Canada. Germany, in turn, has declared that the turbine in question should only be used in September.

On Thursday, two people familiar with the matter said the turbine was blocked in transit to Germany because Russia had not yet given the green light to bring it back.